# Is it possible to map the function from Excel "Workday" in seatable?

**URL:** <https://forum.seatable.com/t/is-it-possible-to-map-the-function-from-excel-workday-in-seatable/2893>\
**Category:** Formulas\
**Created:** [November 8, 2023, 9:03pm UTC](https://forum.seatable.com/t/is-it-possible-to-map-the-function-from-excel-workday-in-seatable/2893 "2023-11-08T21:03:55Z")\
**Posts on this page:** 3\
**Page:** 1

<div class="post-metadata">

**Author:** ![kyraheld](https://forum.seatable.com/letter_avatar_proxy/v4/letter/k/f475e1/32.png) [@kyraheld](https://forum.seatable.com/u/kyraheld)\
**Post date:** [November 8, 2023, 9:03pm UTC](https://forum.seatable.com/t/is-it-possible-to-map-the-function-from-excel-workday-in-seatable/2893/1 "2023-11-08T21:03:56Z")

</div>

Is it possible to map the function from Excel “Workday” in seatable? The syntax from Excel is as follows: =WORKDAY(starting\_date; days; [days\_off])

I have several work phases that have a certain duration and an end date for the overall project. Now I would like the start and end date of the individual phases to be calculated automatically based on the duration and end date of the project. If the duration of a phase changes in the meantime, the start and end dates of the phases should also be adjusted.

---

<div class="post-metadata">

**Author:** ![rdb](https://forum.seatable.com/user_avatar/forum.seatable.com/rdb/32/1869_2.png) [@rdb](https://forum.seatable.com/u/rdb)\
**Post date:** [November 8, 2023, 10:20pm UTC](https://forum.seatable.com/t/is-it-possible-to-map-the-function-from-excel-workday-in-seatable/2893/2 "2023-11-08T22:20:28Z")

</div>

SeaTable has no such function. Sorry.

SeaTable has the dateadd() function ([Formelreferenz - SeaTable](https://seatable.io/docs/formeln/formelreferenz/)), but it does not take weekends and holidays into account.

---

<div class="post-metadata">

**Author:** ![system](https://forum.seatable.com/uploads/default/original/1X/04603423fe81a46c321283663086c475429e8ccb.png) [@system](https://forum.seatable.com/u/system)\
**Post date:** [November 13, 2023, 5:44pm UTC](https://forum.seatable.com/t/is-it-possible-to-map-the-function-from-excel-workday-in-seatable/2893/3 "2023-11-13T17:44:42Z")

</div>

Closed on November 13, 2023, 5:44pm UTC

This topic was automatically closed 2 days after the last reply. New replies are no longer allowed.